Mark your calendars for huge traffic impact: LADWP Bel-Air Power Upgrade Project commences June 18!

Bel Air Upgrade Project PHASE 1 map 800.jpg

As previously posted, LADWP is planning construction to add more circuits that will increase electric capacity in the greater Bel Air area.  This is a much-needed upgrade that will improve reliability in the Bel-Air, Beverly Crest, Westwood, and Holmby Hills neighborhoods.

Construction on Sunset Blvd will begin Tuesday, June 18, 2019, at 9:00 AM.

A few reminders:

·         Construction hours are Monday through Friday 9:00 AM to 3:30 PM, and Saturday 8:00 AM through 6:00 PM. 

·         You can expect to see crews working primarily in the middle two lanes on Sunset Blvd.

·         During construction, at least one lane will be open in each direction to maintain both eastbound and westbound traffic flow.

·         At the end of each work day, all lanes will be reopened to traffic.

·         Crews will be working simultaneously at the following locations:

(1)      Sunset between the 405 Freeway and Bellagio Rd. Crews will begin work near the 405, working about 500 feet at a time and progressing eastward toward Bellagio Rd.

(2)      Sunset between S. Beverly Glen Blvd. and Carolwood Dr.

Click here to link to LADWP’s Fact Sheet.

Bel Air Upgrade Project PHASE 1 fact sheet_Page_1 800.jpg