Construction Activities
Summary of construction activity taking place along the project's alignment.
There will be no work from Thursday to Sunday.
Section 3
Westwood/UCLA Station
🔆Galey Ave. Catch Basin Work | Learn More
🔆Piling and Utility Work at Gayley Ave and Wilshire Blvd | Learn More
Piling on Wilshire Blvd. between Gayley Ave. and Veteran Ave. | Learn More
Westwood Blvd Utility and Pile Installation | Learn More
Westwood Blvd Utility and Pile Installation Activities | Learn More
Westwood/VA Hospital Station
🔆Subsurface Investigation at I-405 On-ramps | Learn More
Ongoing work in Caltrans Basin | Learn More
West LA VA Hospital Campus Worksite Activities | Learn More