NOTICE OF STREET WORK


Starting approximately Wednesday, February 19, 2020, and working through Monday, February 24, 2020, the City of Los Angeles Department of Public Works, Bureau of Street Services will begin roadway improvements on:
 

Bel Air Road, from Nimes to Sunset Boulevard


The first phase will require preparation of the existing roadway by cold milling the street.  The final phase will require paving of the existing roadway and resurfacing the street Monday, February 24, 2020.  If the project length is delayed, you will be notified of the reason for the delay and the revised completion date.

While the project is in progress, “Temporary No Parking signs” will be posted on the street.  The signs will be posted at least 24 hours before the actual work begins to provide notice to residents and business owners.  Please have all vehicles removed from the street to protect them from damage by construction debris and to prevent interference with the planned work.  When work is not in progress between the preparation and resurfacing phases, the signs will be reversed to allow for vehicular parking.

Vehicles will have access during the cold milling of the project.  However, it is requested that driving be limited within the project area to avoid possible damage to your vehicle.  The only time that access will be restricted within the project area is when the street is coated with liquid asphalt prior to the resurfacing of the street.

When the crews are working, there will be construction equipment and trucks in the area.  This equipment may be of interest to children.  Remind residents to be careful and ask children to avoid the equipment and work-site area.

Thank you for your understanding and patience during this project.  Persons with mobility impediments and their caregivers can request assistance if the scheduled street work limits their use (including ingress or egress) of the public right-of-way.  If you have questions or need to request an accommodation, contact the supervisor on the project site or call (818) 756-8651 or (213) 847-3200.

Please note:  If you are planning any improvements to your business or residence that require an excavation in the street, please call one of the above numbers immediately.  Once the street is resurfaced, any excavations within one year after the date of the paving will be prohibited; or will require the resurfacing of the entire block or intersection, depending on the location of the excavation, by the entity performing the excavation and at their cost.  If the street excavation is performed beyond the one-year moratorium period, a graduated fee will apply.  (Street Damage Restoration Fee per LAMC 62.06).