LADWP Utilities Upgrade Project NEW DETOUR MAP: West Gate Road Closure for Leg 3 commences this Monday, November 18, and expects to complete before December 25
SEE LADWP FACT SHEETS AND DETOUR MAPS LINKS BELOW.
The construction for LADWP’s utilities upgrade continues. Leg 1 is completed; Leg 2 finishes up this weekend. Please note that Leg 2 will still have workers present but the Bellagio Road to Sarbonne Road will be open to traffic.
Beginning Monday:
• LEG 3: MONDAY, NOVEMBER 18, begins Leg 3 of upgrade with full road closure at West Gate’s western Bellagio Road from Sunset to Chalon Road, including Bellagio Place and Funchal Road.
What’s next? Leg 4:
Come January to February 2020:
• LEG 4: Commencement date will be in January and end in February. There will be full road closure on Chalon Road between Roscomare Road and Chantilly Road.
Below is LADWP’s announcement and fact sheets:
Dear Bel Air Residents and Stakeholders,
Construction on Bellagio Road will continue through the end of this year. Currently, crews are working on Bellagio Road just north of Sunset (on the west side of the Bel-Air Country Club) to Chalon Road. This will be a full road closure of Bellagio Road, including a small portion of Bellagio Place and Funchal Road.
For residents who live within this road closure: Local Access Passes will be distributed to facilitate ingress and egress. Each household will receive 5 Local Access Passes for family members and designated visitors. Trash service will not be disrupted and deliveries will be allowed.
Work hours are Monday through Friday 8am to 4pm, plus Saturdays 7am to 7pm. There will be no construction on Sundays or holidays. Emergency vehicles will be allowed to pass through the construction zone and flaggers will assist with traffic flow. We will be excavating and trenching – similar to the type of construction that was done on Sunset Blvd over the summer – so please allow extra time to navigate around construction and drive slowly. See attachment page 1 for detour route.
Note that after Bellagio Road construction is completed, we will begin construction on Chalon Road between Roscomare Road and Chantilly Road. The Chalon portion of work will begin after the New Year in 2020. See attachment page 2. Local Access Passes for homes located in the Chalon Road closure will be distributed at a later date.
Please contact us if you have any questions. Thank you.
Bel Air Project Hotline
Calls answered Monday through Friday 8am-4pm
213-367-6045
Click here for detour map of Leg 3 (commencing 11/18/19)
Click here for detour map of January 2020’s Leg 4