Traffic Impact: Caltrans Basin Drainage Work near Southbound I-405 11/9/20 to 2/8/21 will affect Wilshire ramps

Summary

Metro contractors will work in the Caltrans basin near southbound I-405 in preparation for the Purple (D Line) Extension Section 3. The work includes tree removal, excavation, and drainage structure installation from Monday, November 9, 2020 to February 8, 2021 Monday through Friday, 7am to 4pm and 9pm to 6am.

Essentials

Date: November 9, 2020 to February 8, 2021

Work Hours: Monday through Friday, 7am to 4pm and 9pm to 6am

Traffic Controls:  

  • Westbound Wilshire Blvd. to southbound I-405 on-ramp will be closed from 12am to 6am

  • Southbound I-405 to eastbound Wilshire Blvd. off-ramp will be closed from 9am to 2pm and 9pm to 5am

  • Ramp shoulders will be closed during work activities

Noteworthy

  • All work has received necessary permits and approvals.

  • Access to driveways, residences & businesses will be maintained at all times unless notified in advance.

  • Access for pedestrians will be maintained outside of construction zones.

  • Access for the Fire Department and emergency responders will be maintained.

  • Parking restrictions will be implemented in the immediate area of the work zone.

  • For construction related issues needing immediate attention, please call Metro’s 24-hour Hotline at 213.922.6934.