This monthly notification is an outline of construction activities for the Westwood/VA Hospital Station for the month of September 2020. 

  • Utility Relocation on Wilshire Blvd., Ohio Ave. & Federal Ave. 

  • Worksite Preparation on VA Hospital Campus

  • Hauling from VA Hospital Campus 

  • Utility Duct Bank Installation near VA Hospital Campus 

  • Sanitary Sewer and Utility Relocation on Wilshire Blvd. & Federal Ave. 

  • VA Parking Lot Refurbishment

For more information, link here.

Geotechnical Instrumentation Monitor Installation on Sepulveda Blvd.

Summary

Metro contractors will install geotechnical instrumentation monitors on Sepulveda Blvd. in preparation for the Purple Line Extension Section 3. The instrumentation monitors will allow our team to observe tunnel activities and maintain the safety of the project. The installation will be conducted from Monday, August 24 through Friday, September 4, from 9pm to 6am.