METRO: Purple Line Construction Traffic Impact Update

Construction Activities
Summary of construction activity taking place along the project's alignment

🔆denotes a new or updated notice

Section 3
Recent Updates:

Westwood/UCLA Station 

  • 🔆Geotech Instrumentation with Wilshire Lane Closures and I-405 Ramp Closures| Learn More

  • 🔆Piling in UCLA Lot 36 | Learn More

  • Piling on Wilshire Blvd. between Westwood Blvd. and Gayley Ave.| Learn More

  • Sidewalk Closure for UCLA Piling | Learn More

  • 🔆Traffic Signal Light Pole Installation at Wilshire Blvd and Westwood Blvd. | Learn More

  • Restoration of Street Stripping Concluding Sanitary Sewer Relocation | Learn More

  • 🔆Sanitary Sewer Utility Relocation on Gayley Ave. | Learn More

  • 🔆Crane Relocation and Bus Stop Closure: SB Westwood at Wilshire| Learn More

  • 🔆Utility Relocation on Wilshire Blvd. and Gayley Ave. | Learn More

Westwood/VA Hospital Station

  • 🔆Southbound I-405 Shoulder and Ramp Closures| Learn More

  • West LA VA Hospital Campus Worksite Activities | Learn More

  • Ongoing work in Caltrans Basin | Learn More

Construction is a dynamic process and information is subject to change without notice. For the latest construction updates visit our project website. Upcoming Meetings are listed on this page.