Stone Canyon Resurfacing Begins!
We received notice from the city that Stone Canyon resurfacing will begin on approximately Monday, May 2, 2022, the City of Los Angeles, Department of Public Works, Bureau of Street Services will begin roadway improvements on:
Stone Canyon Road, from dead end north of Lindamere Drive to Rocca Way
The first phase will require preparation of the existing roadway by cold milling the streets Monday, May 2, 2022 through Friday, May 6, 2022.
The final phase will require paving of the existing roadway and resurfacing the street Monday, May 9, 2022 through Friday, May 13, 2022. If the project length is delayed, you will be notified of the reason for the delay and of the revised completion date. While the project is in progress, “Temporary No Parking Signs” will be posted on the street. The signs will be posted at least 24 hours before the actual work begins to provide notice to residents and business owners. Please have all vehicles removed from the street to protect them from damage by construction debris and to prevent interference with the planned work. When work is not in progress between the preparation and resurfacing phases the signs will be reversed to allow for vehicular parking.
Stone Canyon Road, from Rocca Way to Sunset Boulevard
The first phase will require preparation of the existing roadway by cold milling the streets Wednesday, May 4, 2022 through Monday, May 9, 2022. The final phase will require paving of the existing roadway and resurfacing the street Wednesday, May 11, 2022 through Monday, May 16, Monday. If the project length is delayed, you will be notified of the reason for the delay and of the revised completion date.
Vehicles will have access during the cold milling of the project. However, it is requested that driving be limited within the project area to avoid possible damage to your vehicle. The only time that access will be restricted within the project area is when the street is coated with liquid asphalt, prior to the resurfacing of the street.